Requires the office of renewable energy siting and electric transmission to establish a mapping, installation and efficiency plan for the purpose of building new electric transmission lines

Bill record: Open States bulk CSV (bills/votes) CC0-1.0

Summary AI-generated

New York Bill S 2485 requires the Office of Renewable Energy Siting and Electric Transmission to establish a mapping, installation, and efficiency plan. The purpose of this plan is to facilitate the building of new electric transmission lines.

Software-generated, grounded only in the bill's own fields (it does not invent outcomes, amounts, or dates). Provenance: Open States bulk CSV (bills/votes) CC0-1.0 GovTally LLM enrichment (local oMLX)

Issue tags AI-classified

Classified by a local model from the bill's text; confidence shown. GovTally LLM enrichment (local oMLX)

Sponsors

Roll-call votes on this bill

QuestionChamberResultYeaNayOtherDateSource
Floor Vote upper pass 43 17 3 May 12, 2026 Open States bulk CSV (bills/votes) CC0-1.0
Finance Vote upper pass 18 2 2 Apr 28, 2026 Open States bulk CSV (bills/votes) CC0-1.0
Energy And Telecommunications Vote upper pass 8 1 0 Feb 3, 2026 Open States bulk CSV (bills/votes) CC0-1.0
Floor Vote upper pass 42 15 4 Jun 13, 2025 Open States bulk CSV (bills/votes) CC0-1.0
Rules Vote upper pass 17 2 1 Jun 12, 2025 Open States bulk CSV (bills/votes) CC0-1.0
Energy And Telecommunications Vote upper pass 8 1 0 Apr 28, 2025 Open States bulk CSV (bills/votes) CC0-1.0